Tlestew 36 blokka ta akkomodazzjoni soċjali minn 79 fl-2026

ilpolz

Tlestew 36 blokka ta akkomodazzjoni soċjali minn 79 fl-2026

Il-Fatti

Il-Ministru għall-Akkomodazzjoni u l-Artijiet ppreżenta aġġornament parlamentari dwar il-programm ta manutenzjoni għall-Housing Estates tal-Gvern. Sa 31 ta Mejju 2026, tlestew xogħlijiet fuq 36 blokka minn total ta 79 blokka previsti għas-sena 2026, li jammontaw għal 45.6 fil-mija tal-programm annwali.

Matul is-snin preċedenti, il-programm ta manutenzjoni u tisbiħ mexa kif ġej: Fl-2024, tlestew xogħlijiet fuq total ta 74 blokka f lokalitajiet inklużi l-Ħamrun, il-Fgura, San Ġiljan, Bormla, Birkirkara, u ż-Żejtun. Fl-2025, tlestew xogħlijiet fuq total ta 60 blokka f lokalitajiet inklużi l-Gudja, San Ġwann, Santa Luċija, il-Marsa, Ħal Tarxien, u Raħal Ġdid. Bejn is-sena 2018 u 31 ta Mejju 2026, ġew indirizzati total ta 589 blokka madwar Malta u Għawdex.

Xi Jfisser Ghalik

Il-proġett ta manutenzjoni jaffettwa direttament il-kundizzjoni fiżika tal-bini residenzjali tal-Gvern. L-inkwilini li jgħixu fil-blokok elenkati jistgħu jistennew titjib fl-infrastruttura tal-bini tagħhom hekk kif il-programm ikompli jiġi implimentat matul il-bqija tas-sena 2026. L-istatus ta progress ivarja skont il-lokalità, b xi żoni laħqu l-100 fil-mija ta tlestija u oħrajn għadhom fil-fażi inizjali.

Il-Kwistjoni

Mhemmx diverġenza sinifikanti bejn is-sorsi, iżda l-progress fil-lokalitajiet individwali għas-sena 2026 juru diskrepanzi kbar. Filwaqt li l-Mosta laħqet 100 fil-mija, il-Gżira, il-Kalkara, u Ħal Għaxaq għadhom f 0 fil-mija ta tlestija sa 31 ta Mejju 2026.

L-Istampa l-Kbira

Il-Gvern qed ikompli programm kontinwu ta tisbiħ u manutenzjoni għall-istokk tal-akkomodazzjoni soċjali li ilu għaddej mill-inqas mill-2018. Dan l-investiment huwa parti mill-istrateġija nazzjonali biex jinżamm l-istandard tal-bini pubbliku u jiġu indirizzati l-bżonnijiet ta manutenzjoni strutturali għal mijiet ta familji.

Dettalji Ewlenin

  • Total ta blokok manutenzjoni 2018 sa 2026: 589

  • Total ta blokok skedati għall-2026: 79

  • Total ta blokok kompluti għall-2026 sal-31 ta Mejju: 36

  • Perċentwal ta progress għall-2026 sal-31 ta Mejju: 45.6 fil-mija

  • Status Mosta 2026: 100 fil-mija

  • Status Marsaskala 2026: 85 fil-mija

  • Status Ta Xbiex 2026: 57.6 fil-mija

  • Status Paola 2026: 42.4 fil-mija

  • Status Attard 2026: 39.3 fil-mija

  • Status Żejtun Ħal Tmin 2026: 20 fil-mija

  • Status Ħal Għaxaq 2026: 9.7 fil-mija

  • Status Gżira 2026: 0 fil-mija

  • Status Santa Luċija 2026: 0 fil-mija

  • Status Kalkara 2026: 0 fil-mija

Affiljat

Tqatta' ħafna sigħat taqra l-aħbarijiet fuq l-iskrin? Ipproteġi l-għajnejn tiegħek

b'nuċċali li jimblukkaw id-dawl blu. Ikseb il-par tiegħek illum.

https://amzn.to/4uRaUuk

Disklaimer Il-Polz

Din l-aħbar hija bbażata fuq kontroll ta' sorsi pubbliċi u informazzjoni uffiċjali.

Mhijiex parir professjonali. Il-fatti jistgħu jinbidlu hekk kif joħorġu aġġornamenti

ġodda. Għal aktar dettalji u ċ-ċitazzjonijiet sħaħ, żur ir-Reġistru tas-Sorsi

Verifikati fuq Il-Polz: https://ilpolz.fika.bar/

Facebook: https://www.facebook.com/ilpolz

═════ ENGLISH VERSION ═════

36 social housing blocks completed out of 79 in 2026

The Facts

The Minister for Housing and Lands presented a parliamentary update regarding the maintenance project for Government Housing Estates. As of May 31, 2026, works have been completed on 36 blocks out of a total of 79 blocks planned for 2026, representing 45.6 percent of the annual program.

Over previous years, the maintenance and embellishment program proceeded as follows: In 2024, works were completed on a total of 74 blocks in localities including Hamrun, Fgura, San Giljan, Bormla, Birkirkara, and Zejtun. In 2025, works were completed on a total of 60 blocks in localities including Gudja, San Gwann, Santa Lucija, Marsa, Tarxien, and Rahal Gdid. Between 2018 and May 31, 2026, a total of 589 blocks were addressed across Malta and Gozo.

What It Means

The maintenance project directly affects the physical condition of government residential buildings. Tenants living in the listed blocks can expect infrastructure improvements as the program continues throughout the remainder of 2026. Progress status varies by locality, with some areas reaching 100 percent completion and others remaining in the initial phase.

Different Views

There is no significant divergence between sources, but progress in individual localities for 2026 shows large discrepancies. While Mosta reached 100 percent, Gzira, Kalkara, and Hal Ghaxaq remain at 0 percent completion as of May 31, 2026.

Big Picture

The Government is continuing an ongoing embellishment and maintenance program for social housing stock that has been in place since at least 2018. This investment is part of the national strategy to maintain the standard of public buildings and address structural maintenance needs for hundreds of families.

Key Points

  • Total blocks maintained 2018 to 2026: 589

  • Total blocks scheduled for 2026: 79

  • Total blocks completed for 2026 as of May 31: 36

  • Progress percentage for 2026 as of May 31: 45.6 percent

  • Status Mosta 2026: 100 percent

  • Status Marsaskala 2026: 85 percent

  • Status Ta Xbiex 2026: 57.6 percent

  • Status Paola 2026: 42.4 percent

  • Status Attard 2026: 39.3 percent

  • Status Zejtun Hal Tmin 2026: 20 percent

  • Status Hal Ghaxaq 2026: 9.7 percent

  • Status Gzira 2026: 0 percent

  • Status Santa Lucija 2026: 0 percent

  • Status Kalkara 2026: 0 percent

Affiliate

Spending many hours reading news on your screen? Protect your eyes with blue-light

blocking glasses. Get your pair today.

https://amzn.to/4uRaUuk

Disclaimer Il-Polz

This news is based on a check of public sources and official information. It is not

professional advice. Facts may change as new updates emerge. For full details and

citations, visit the Verified Source Registry at Il-Polz: https://ilpolz.fika.bar/

Facebook: https://www.facebook.com/ilpolz

═════ DEUTSCHE VERSION ═════

36 Sozialwohnungsblöcke von 79 im Jahr 2026 fertiggestellt

Die Fakten

Der Minister für Wohnungswesen und Ländereien legte ein parlamentarisches Update zum Wartungsprojekt für staatliche Wohnsiedlungen vor. Zum 31. Mai 2026 wurden Arbeiten an 36 Blöcken von insgesamt 79 für 2026 geplanten Blöcken abgeschlossen, was 45,6 Prozent des Jahresprogramms entspricht.

In den Vorjahren verlief das Wartungs- und Verschönerungsprogramm wie folgt: Im Jahr 2024 wurden Arbeiten an insgesamt 74 Blöcken in Ortschaften wie Hamrun, Fgura, San Giljan, Bormla, Birkirkara und Zejtun abgeschlossen. Im Jahr 2025 wurden Arbeiten an insgesamt 60 Blöcken in Ortschaften wie Gudja, San Gwann, Santa Lucija, Marsa, Tarxien und Rahal Gdid abgeschlossen. Zwischen 2018 und dem 31. Mai 2026 wurden insgesamt 589 Blöcke in ganz Malta und Gozo behandelt.

Was das bedeutet

Das Wartungsprojekt wirkt sich direkt auf den physischen Zustand staatlicher Wohngebäude aus. Mieter, die in den aufgelisteten Blöcken wohnen, können mit Infrastrukturverbesserungen rechnen, während das Programm für den Rest des Jahres 2026 fortgesetzt wird. Der Fortschrittsstatus variiert je nach Ortschaft, wobei einige Gebiete 100 Prozent Fertigstellung erreicht haben und andere sich noch in der Anfangsphase befinden.

Verschiedene Ansichten

Es gibt keine wesentlichen Abweichungen zwischen den Quellen, aber der Fortschritt in den einzelnen Ortschaften für 2026 zeigt große Diskrepanzen. Während Mosta 100 Prozent erreichte, liegen Gzira, Kalkara und Hal Ghaxaq zum 31. Mai 2026 noch bei 0 Prozent Fertigstellung.

Das große Ganze

Die Regierung setzt ein fortlaufendes Verschönerungs- und Wartungsprogramm für den Sozialwohnungsbestand fort, das seit mindestens 2018 besteht. Diese Investition ist Teil der nationalen Strategie, den Standard öffentlicher Gebäude aufrechtzuerhalten und den strukturellen Wartungsbedarf für Hunderte von Familien zu decken.

Wichtige Punkte

  • Gesamtzahl gewarteter Blöcke 2018 bis 2026: 589

  • Gesamtzahl der für 2026 geplanten Blöcke: 79

  • Gesamtzahl der für 2026 bis zum 31. Mai fertiggestellten Blöcke: 36

  • Fortschrittsprozentsatz für 2026 bis zum 31. Mai: 45,6 Prozent

  • Status Mosta 2026: 100 Prozent

  • Status Marsaskala 2026: 85 Prozent

  • Status Ta Xbiex 2026: 57,6 Prozent

  • Status Paola 2026: 42,4 Prozent

  • Status Attard 2026: 39,3 Prozent

  • Status Zejtun Hal Tmin 2026: 20 Prozent

  • Status Hal Ghaxaq 2026: 9,7 Prozent

  • Status Gzira 2026: 0 Prozent

  • Status Santa Lucija 2026: 0 Prozent

  • Status Kalkara 2026: 0 Prozent

Affiliate

Verbringen Sie viele Stunden damit, Nachrichten auf Ihrem Bildschirm zu lesen?

Schützen Sie Ihre Augen mit Blaulichtfilterbrillen. Holen Sie sich noch heute

Ihr Exemplar.

https://amzn.to/4uRaUuk

Haftungsausschluss Il-Polz

Diese Nachricht basiert auf einer Überprüfung öffentlicher Quellen und offizieller

Informationen. Sie stellt keine professionelle Beratung dar. Fakten können sich

ändern, sobald neue Aktualisierungen vorliegen. Für weitere Details und

vollständige Zitate besuchen Sie das Register der verifizierten Quellen auf

Il-Polz: https://ilpolz.fika.bar/

Facebook: https://www.facebook.com/ilpolz

Subscribe to "Il-Polz" to get updates straight to your inbox
ilpolz

Subscribe to ilpolz to react

Subscribe

Comments

No comments yet. Be the first to comment!

Subscribe to Il-Polz to get updates straight to your inbox